FROM THE OCEAN GROVE HOMEOWNERS ASSOCIATION :
“It may be hard to believe, but the Broadway Drainage Project has reached its final phase: milling and paving the roadway from Lawrence Avenue east to Ocean Avenue.
“All that remains to be done prior to the start of paving is to (1) complete work on the sewer line at the east end of Broadway; and (2) lay the conduit that will hold the electrical wiring for the new street lights. Work on the sewer line is expected to be complete by April 19 (weather permitting); and the conduit to be laid by April 26 (weather permitting).
“In order to expedite milling and paving, there will be no parking on either side of Broadway from Monday, April 29 through Friday, May 3.”
Broadway residents will be receiving detailed information from Neptune Township PD. Paving should be done by May 3.